Update Center

US
290 element delayed by funding crisis
Need for Hempstead Managed Use lanes now paramount
US 290 Project Information
Website (TxDOT)
Hempstead Toll Road by HCTRA
US 290 DEIS
Map Sections
Metro Operating Cypress Park & Ride Service
The Draft Environmental Impact Statement is
available at
this link
TxDOT project website can be viewed at this link
www.my290.com
Overview of US 290 and Hempstead Corridor from
Loop 610 to FM 2920


Following the completion of the management investment study (MIS) of
the US 290 corridor, TxDOT completed a Draft Environmental Impact Statement
which is awaiting approval by the Federal Highway Administration.
The MIS evaluated the future
transportation needs of the Corridor and evaluated alternatives in addressing
transportation issues. The MIS evaluated various transportation alternatives to
determine which alternatives were best to address congestion, traffic safety,
and environmental issues along the Corridor.
This MIS was begun in 1999 and was completed in 2002.
Following the review of over 11 alternative treatments and three major public
meetings with a total attendance of nearly 1000 residents and workers in the
corridor, a recommended alternative was selected.
Preferred Alternative
The preferred alternative is to widen US 290 to 5 general
purpose lanes in each direction between Loop 610 and the Grand Parkway. In
addition, it proposes 4 general purpose lanes from the Grand Parkway to FM 2920.
The preferred alternative also contains "advanced
high-capacity transit" along Hempstead inside Beltway 8 and along US 290 outside
BW 8.
In addition the alternative calls for a 4 lane, two-way,
managed use facility along Hempstead. This concept is similar to that
being constructed in the Interstate 10 West corridor. The difference is
that the Hempstead facility will not be in the center of the freeway as is the
I-10 project. Click on these thumbnails for a schematic


Potential Changes to project cross sections

Current Developments
TxDOT is experiencing a severe funding crisis resulting in
cutbacks in current projects and delays for future projects such as US 290.
This suggests the
expansion of US 290 proper will be delayed placing more pressure on the toll
financed managed use lanes to be built in on the Hempstead alignment.
The project is entering preliminary design and the connection
of US 290 at Loop 610 to Interstate 10 West is being redesigned to improve
traffic flow in that highly congested corridor.
In addition, an evaluation is underway on the Hempstead
managed use lanes as a tolled project, again similar to the managed use lanes on
Interstate 10 West.
The Hempstead/US-290 Managed Lane project is a 22 mile
project, extending from IH-610 to SH-99 (Grand Parkway). The schematic
engineering will be completed Fall 2007. The final engineering will begin Spring
2008 and be completed Summer 2014. Construction will begin Spring 2010 and be
completed Spring 2014. The estimated construction cost is $550 Million; When
completed, the managed lanes will provide 2 lanes in each direction. This
project is dependent upon a formalized agreement with TxDOT.
A major concern of the West Houston Association is the design
of grade separations in the corridor. We believe the major thoroughfares
crossing both US 290 and Hempstead should be grade separated to improve mobility
in the entire corridor.
|